Engineering Standards

Our Standards

A wall is made up of five layers and the eye sees only the outermost one. What really decides how the home lives — how high the waterproofing goes, whether the pipes were pressure tested, whether the wiring is all new — sits behind that layer, and once it is closed up it cannot be looked at again. So every layer carries a standard that can be measured, and each one is photographed and filed as soon as it is finished.

01 — Wall build-up

One wall, five layers

The table below runs from the innermost structural layer (01) out to the finish layer (05), which is the actual order of site works; demolition goes the other way, starting from the finish you can see and working inwards layer by layer. Select any layer and it will be marked on the diagram.

Wall Build-up · section through the wall layers A-01
01 02 03 04 05 Isometric interior section · schematic, not to scale
Galaxy Interior Design Rev. 2026-08
  • The interior once the finishes are complete
    The interior once the finishes are complete

    ≤1mm

    Tile lippage

    ≥1.5mm

    Movement joints

    ≤20%

    Hollowness per tile

    Correct method

    Tiles are laid to the tile setting-out drawing, with external corners and skirtings mitred throughout; before painting, surfaces are scraped back to remove all old paint and skim coat that hand tools can take off.

    Wrong method

    With no movement joints in the tile joints, the tiles tent as they expand and contract; hollow tiles laid without being dealt with crack underfoot later.

    Reference: Architectural Services Department General Specification for Building (2007), BS 5385 Part 1, BS 6150:2019

02 — Works sequence timeline

Demolition to completion takes about 21 weeks. Tap any stage to see the key points for that gate and the evidence that has to be submitted; until it is all in, the next stage does not begin.

Programme breakdownAbout 21 weeks from demolition to completion
DemolitionAbout 1 week About 1 week
Electrical & plumbing · installation and pressure testingAbout 6 weeks About 6 weeks
Wet trades · plastering and drainage fallsAbout 1 week About 1 week
Waterproofing · ponding testUnder 1 week Under 1 week
Painting · scraping back the old surfaceAbout 3 weeks About 3 weeks
Carpentry · furniture installationAbout 5 weeks About 5 weeks
Completion · handover inspectionAbout 3 days About 3 days
Week 4Week 8Week 12Week 16Week 20

Bar lengths are scaled from actual site records; dashed bars are approximate. The gaps between stages are time spent waiting for materials and for other trades.

Demolition · stripped back to the structure

Stage 01

Demolition · stripped back to the structure

  • Old finishes and old pipework removed
  • Checked on site for seepage, exposed wiring and rebar corrosion
  • Water valve closed, then the gas appliance removed by a gas technician
  • Items to be kept are photographed, then wrapped
To pass: photos before and after demolition; records and protection for items to be kept (water heater/air-conditioner/window sill stone/metal gate)
03 — Where works go wrong

Six common site pitfalls

The six items below are where renovation work most often goes wrong. Tap each card to see where the risk sits and how we handle it.

Registered Professional Engineer

The company is led by Registered Professional Engineer Andrew Lai; our standards are set and reviewed by the engineer.

Registered Minor Works Contractor

We can carry out works notified under the Minor Works Control System, including Class 1 and 2 items that require prior notification.

ISO 9001:2015 Quality Management System

Scope of certification: Interior Design & Fitting-Out.

Certificate no. AQ0319 · valid to 20 December 2028

Want to know which layers in your home need the closest attention?

Buildings of different ages and orientations fail in different places. Send us the sales brochure or the floor plan and we can tell you first what has to be done and what can be left out.